Bally’s Secures $560 Million in Financing for Chicago Casino
The package arrives as terminal competition and construction costs challenge the project.

Key Takeaways
- Bally’s Corporation secured $560 million in additional financing for its $1.7 billion Chicago casino development.
- Gaming and Leisure Properties committed $60 million in additional development funding, subject to regulatory approval, bringing its total commitments to $1 billion.
- Bally’s reduced work on non-gaming facilities after the Illinois Gaming Board approved 65 video gambling terminal applications in Chicago.
- The permanent Chicago casino requires approximately $400 million in construction spending over the next two years.
Bally’s Corporation has secured $560 million in additional financing as it works towards opening its permanent Chicago casino resort, a $1.7 billion development. The package includes $500 million in new loans and $60 million in development funding, while roughly $400 million in construction costs remain.
How the financing is allocated
The $500 million consists of second-lien loans intended for debt repayments and corporate expenses. Gaming and Leisure Properties (GLPI) has committed a further $60 million to the Chicago development, subject to regulatory approval. That agreement brings GLPI’s total commitments to $1 billion.
The financing comes amid financial difficulties for Bally’s. The operator reported a $56.4 million loss in the first half of 2026 and an accumulated deficit of $233.3 million. In August, it warned that its debt raised:
“substantial doubt about its ability to continue” over the following year. — Bally’s Corporation
Bally’s temporary casino at Medinah Temple, 600 N. Wabash Ave., has struggled to break even.
Video terminal dispute slows work
Construction at 777 W. Chicago Ave. faces a separate dispute over video gambling terminals. Bally’s reduced work on non-gaming facilities in August after the Illinois Gaming Board approved 65 video gambling terminal applications in Chicago.
Bally’s executives raised their concerns at a September Chicago City Council hearing, arguing that terminals in bars and other locations could:
“cannibalize” casino revenue. — Bally’s executives
At the hearing, executives maintained that financing was available to complete the resort. A dispute over the terminals has delayed parts of the project.
Remaining construction costs
The permanent Bally’s Chicago casino still needs approximately $400 million in construction spending over the next two years. Its estimated development cost is $1.7 billion.
Under Illinois gambling rules, video gambling terminals and casinos operate under separate licensing arrangements. Permitting terminals across Chicago creates additional competition for the planned casino.
Frequently Asked Questions
What will Bally’s use its new $500 million loan for?
Bally’s intends to use the $500 million in second-lien loans for debt repayments and corporate expenses. The loans form part of a $560 million financing package.
How is Bally’s temporary Chicago casino performing?
Bally’s temporary casino at Medinah Temple has struggled to break even. It is located at 600 N. Wabash Ave.
What financial difficulties has Bally’s reported?
Bally’s reported a $56.4 million loss in the first half of 2026 and an accumulated deficit of $233.3 million. In August, it warned that its debt raised substantial doubt about its ability to continue over the following year.
Why is Bally’s concerned about video gambling terminals in Chicago?
Bally’s executives argue that terminals in bars and other locations could cannibalize casino revenue. They raised the concern at a September Chicago City Council hearing, where they also maintained that financing was available to complete the resort.
Tags
About the author

Oliver Grant
Industry Technology Correspondent
Oliver Grant covers the technology and business machinery of iGaming — platform and data deals, AI and compliance tooling, affiliate and marketing shifts, and the quarterly numbers behind them. The reports lead with the announcement, name the vendors and figures exactly as published, and separate genuine capability from press-release promise. When a supplier ships a new engine or a regulator tightens ad rules, Oliver Grant explains what actually changes for the companies involved.